Verified
| Edition in force | 2020 NEC (NFPA 70) adopted through the 2022 Connecticut State Building Code (2021 I-Code based), with Connecticut amendments |
| Edition structure | One statewide edition |
| Effective date | 2022-10-01 |
| Date as recorded | 2022-10-01 (applies to permit applications filed from this date) |
| Adopted by | Connecticut State Building Inspector, Department of Administrative Services (DAS), under Conn. Gen. Stat. s.29-252 with the Codes and Standards Committee |
| Adoption source | http://portal.ct.gov/das/knowledge-base/articles/ctbuys/safety-codes-and-inspections/connecticut-state-building-codes-adoption-process |
| State amendments | State amendments at their own official document — https://portal.ct.gov/das/home/office-of-state-building-inspector/connecticut-state-building-code/regulations?language=en_US |
| Model | State licensing through the Department of Consumer Protection (DCP), Occupational & Professional Licensing, with the Electrical Work Examining Board (Conn. Gen. Stat. ch. 393) |
| Authority | Connecticut Department of Consumer Protection, Occupational & Professional Licensing Division; Electrical Work Examining Board |
| Licensing source | https://portal.ct.gov/DCP/Occupational-and-Professional-Division/Occupational--Profess/Careers-in-the-Trades-License-Types |
| License classes | https://portal.ct.gov/DCP/Occupational-and-Professional-Division/Occupational--Profess/Careers-in-the-Trades-License-Types |
Not yet recorded.
| Adoption | Verified |
| Amendments | Verified |
| Licensing | Verified |
| Permits & inspections | Verified |
grace period → 2023 NEC
When the delayed codes take effect, DAS describes a roughly three-month modification/grace route for projects to continue under the 2022 codes. No end date is stated; none is calculated.
adoption delay → 2023 NEC
The next Connecticut codes would adopt the 2023 NEC; effectiveness is delayed pending Legislative Regulation Review Committee approval. In force remains 2020.
PENDING STRUCTURE (do not promote): DAS's code-change page states the next codes (2026 CSBC, which would adopt the 2023 NEC) were expected July 1, 2026 but the effective date 'has been delayed' pending Legislative Regulation Review Committee approval - so as of retrieval the in-force code remains the 2022 CSBC / 2020 NEC, recorded here. When the 2026 codes do take effect, DAS describes a roughly three-month modification ('grace') route for projects to continue under the 2022 codes. License classes on the official DCP license-types page include E-1 (unlimited electrical contractor) and E-2 (unlimited journeyperson) plus limited electrical classes. Permits/inspections are by local building officials under the state code; no state permit regime was established.
Reference only. Compiled from the cited official sources as of the date shown; adoptions and rules change. Confirm with the authority having jurisdiction before designing or permitting work.