Verified
| Edition in force | 2020 NEC (NFPA 70-2020) with NC state amendments - NC State Electrical Code; the 2017 NC State Electrical Code (2017 NEC) still applies to one- and two-family dwellings |
| Edition structure | Edition split by scope |
| State code | NC State Electrical Code |
| Effective date | 2021-11-01 |
| Date as recorded | 2021-11-01 (2020 code); 2018-06-12 (2017 code, one- and two-family dwellings) |
| Adopted by | North Carolina Building Code Council; administered by the NC Department of Insurance, Office of State Fire Marshal (State Electrical Division) |
| Adoption source | https://www.ncosfm.gov/codes/codes-current-and-past |
| State amendments | State amendments at their own official document — https://www.ncosfm.gov/electrical/2020-approved-amendments-electrical-code/open |
| Model | State licensing of electrical contracting - a state license in an applicable classification is required to engage in electrical contracting (G.S. 87-43); classifications: Limited, Intermediate, Unlimited, plus Special Restricted classifications and a single-family detached residential dwelling license |
| Authority | North Carolina State Board of Examiners of Electrical Contractors (NCBEEC) |
| Licensing source | https://www.ncbeec.org/g-s-87-43-electrical-contractors-licensing-law/ |
| License classes | https://www.ncbeec.org/licensing/ |
2020 NC State Electrical Code s.10.4: permits, inspections (rough-ins and finals), and Certificates of Electrical Compliance are governed by local ordinances and the North Carolina Administrative Code and Policies; there is no separate state electrical permit.
| Adoption | Verified |
| Amendments | Verified |
| Licensing | Verified |
| Permits & inspections | Verified |
| one- and two-family dwellings | 2017 NEC · from 2018-06-12
The 2017 code still applies to one- and two-family dwellings. |
| all work except one- and two-family dwellings | 2020 NEC · from 2021-11-01
2020 NC State Electrical Code. |
adoption delay → 2023 NEC
The adopted 2023 NEC is indefinitely delayed by Session Law 2025-2 and is not in effect; it must never be silently dated.
Split-edition state - do not flatten: 2023 NEC was adopted (Building Code Council 2023-12-12; Rules Review Commission 2024-02-28) but is INDEFINITELY DELAYED by Session Law 2025-2 (HB 47) s.5.12 and is not in effect. Classifications and value caps (Limited $60,000 actual / $100,000 statutory ceiling; Intermediate $150,000 / $200,000, per Board annotation) are verified on the G.S. 87-43 page; the Board's /licensing/ page itself returned a browser 429 this pass and was not opened.
Reference only. Compiled from the cited official sources as of the date shown; adoptions and rules change. Confirm with the authority having jurisdiction before designing or permitting work.